The following pictures show several views from the tower crane, moving
clockwise from the west.
West Section
|
Western section, looking west: The third-floor roof provides storage
space, particularly for materials related to the ventilation and exhaust
shutdown in mid August. The roof of the 1951 wing (chemistry and biology)
is in the upper left.
|
|
South western section: A closer view of the area on the roof of the 1951
wing scheduled for work during the ventilation/exhaust shutdown in mid August.
|
South Western Section
|
South western section: The Science Building elbow
|
|
Southern Section: The southern part of the existing Science Building, about
the 1964 wing. Work focuses on redoing much of the ventilation system.
|
Courtyard and Greenhouse
|
Courtyard: The new courtyard with the existing Science building at the
top of the picture. Work in the courtyard itself involves bringing a new steam line into
an old steam tunnel.
|
|
Greenhouse: Waterproofing protects the floor of the greenhouse.
|
East Section
|
Eastern Section: The roof the third floor section (above computer
science), with the chiller plant at the top.
|
|
North Eastern Section: The northeastern side of the building, facing Eighth
Avenue.
|
North Section: This section will become the Science Library.
|
|
North Western Section: Portable scaffolding along the northern side of the
building has been used by the masons for waterproofing. Brick work will come next.
|